SELF-SUPPLY & PROCUREMENT

Self-generated electricity.
Remaining electricity needs.
One complete picture.

A PV system changes when your company needs grid electricity. Here's how to align self-consumption, storage requirements, and your residual electricity contract with the same operational workflow.

Read article ↓All articles →
Schematic infographic: Direct consumption – use generated electricity in the business as it is produced; Storage – define its purpose and availability; Grid top-up electricity – reflect the remaining profile in the contract.
PV & RESIDUAL ELECTRICITY
  1. Direct consumptionUse generation on site as it occurs
  2. StorageSet task and availability
  3. Residual electricityMap remaining profile in contract
OPTUM / PRACTICEPV & RESIDUAL ELECTRICITY

Self-generated electricity also changes electricity procurement

The photovoltaic system is planned, and the electricity contract continues. At this point, the two projects should be considered together. The external procurement process doesn't simply result in the same demand with a smaller annual sum. Solar generation, operating times, and potential storage options all change when your company needs electricity from the grid.

This section therefore focuses on integrating in-house generation into the procurement process. The design of the system, grid connection issues, and the specific metering concept also belong in the specialist planning. A common data basis is helpful for purchasing: load profile, expected generation, commissioning, and planned control system.

Self-generation changes grid imports. The crucial factor is when solar power and consumption match – and what residual demand remains. AI visualization

Place production and demand on the same time axis

High annual production does not necessarily guarantee a corresponding simultaneous supply for operations. On a sunny weekend, there might be surplus electricity, while an early shift on Monday requires grid power. Therefore, compare production and consumption over the same time intervals. Direct consumption is the solar power your business uses during generation. Feed-in is the surplus that goes into the public grid. Grid imports is the additional energy supplied from the grid. These three quantities should be clearly identifiable in your planning.

In its dossier "More than just electricity from the roof," dena describes how energy management makes energy flows visible and can combine flexible consumers with generation. Crucial factors are the operational load profile and the actually controllable systems. Source: dena/KEDi on energy management with photovoltaics.

What task should the storage device perform?

Increased self-consumption, time shifting, and limiting peak loads are different objectives. Determine which takes priority and when power or stored energy must be available to achieve it. A storage system currently being used for another purpose cannot simultaneously absorb every peak load without limit.

The German Energy Agency (dena) points out that storage size, available surplus energy, and usage must be compatible. Oversized storage systems, despite their technical functionality, can be economically unfavorable. Further information: KEDi dossier, section on electricity storage. In your calculations, also consider losses, usable capacity, operating conditions, and costs.

When choosing a storage system, pay attention to two specifications: The usable capacity in kWh describes the available amount of energy. The charging and discharging power in kW limits how quickly this energy can be absorbed or released. Therefore, a different storage system may be suitable for a short, high power peak than for supplying a long evening shift. Additionally, the control system must determine which task it prioritizes in case of conflicts.

Reflect the remaining requirements in the contract

A simplified example without storage: A company needs 200 MWh per year. A PV system generates 100 MWh; of this, 60 MWh are used directly in the business and 40 MWh are fed into the grid. The remaining grid imports in this example is 140 MWh. The annual generation alone would therefore have made the grid imports appear too low.

This example also distinguishes between two often confused key figures: The direct self-consumption rate is 60 out of 100 MWh, or 60 percent of the PV generation. However, in relation to operational consumption, the system covers 60 out of 200 MWh, or 30 percent. A high self-consumption rate therefore does not automatically mean that the business can largely manage without grid electricity.

Discuss with the supplier how a changed grid-import profile, volume deviations and the commissioning date will be considered. Also ask what happens if commissioning is delayed or the installation is out of service for an extended period. Before making a commitment, the existing supply contract, arrangements for selling generated electricity and the new operating plan should be aligned.

Compare with real data after commissioning

After commissioning, comparison with measured values shows whether the plan holds up. Regularly compare forecast and measured generation, direct consumption and grid imports. Attribute significant deviations to weather, operational changes or technical causes where the data allows this. Record, for example, an additional shift or an inverter failure against the affected period. This helps distinguish one-off deviations from lasting changes in demand for the next procurement period.

For connections with demand metering, the analysis of peak loads and network charges complements the quantity calculation. A dynamic tariff, in turn, requires a separate evaluation of price and load profiles. OPTUM integrates these relationships into the framework of electricity procurement for businesses, ensuring that self-supply and external purchases are planned on the same basis.

SUITABLE FOR YOUR QUESTION

Delve deeper into what will move you forward.

Grid load and residual load: understanding SMARD dataCompare grid load and residual load using published SMARD series: understand terms, units, data gaps and the link to business energy procurement.
Read more →
On-site charging: peak loads and electricity procurementBring together charging needs, vehicle parking times and available site power: include electric mobility in your business’s electricity procurement.
Read more →
SHARING KNOWLEDGE

CLARITY BEFORE SIGNING

You know the terms and conditions.
Before you sign.

We work with you to develop a solution tailored to your business, goals, and security needs. You'll receive our vetted recommendation, complete with comprehensive data and concrete offers. You'll see which price components are fixed, which are variable, and the criteria we use to select suppliers. We document all agreements with you in a transparent and easily understandable manner.

Discuss procurement

OPTUM in the community

What would you like to know?

Enter a term or choose an entry point.

No registration required. The search remains in your browser.